20 men can do a piece of work in 18 days. They worked together for 3 days, then 5 men joined. In how many days is the remaining work completed ?
A.
12 days
AnswerB.
14 days
C.
13 days
D.
15 days
Answer: Option A
Solution
Answer: Option A
Solution:
20 men → 18 days⇒ Work done by 20 men working
Together = 1 work
⇒ Work done by them in 3 days working
Together = 1 × 3 = 3 work
⇒ Remaining work = 18 - 3 = 15 work
⇒ 15 work is to be done by (20 + 5) = 25 men
Therefore, 12 more days will be taken to finish the remaining work
Alternate : 20 men can do 18 days
So, total work = 18 × 20 = 360
20 men 3 days work = 20 × 3 = 60
Remaining work = 360 - 60 = 300
After joining 5 men total men = 20 + 5 = 25
So, finish the remaining work in =