30 labourers working 7 hours a day can finish a piece of work in 18 days. If the labourers work 6 hours a day, then the number of labourers to finish the same piece of work in 30 days, will be ?

A.
15
B.
21
Answer
C.
22
D.
25

Answer: Option B

Solution

Answer: Option B
Solution:
Let the required number of labourers be x
Less working hour/day, More labours (Indirect proportion)
More days, Less labourers (Indirect proportion)