Q25
30 men can do a piece of work in 16 days. How many men would be required to do the same work in 20 days ?
A.
12
B.
24
AnswerC.
36
D.
48
E.
None of these
Answer: Option B
Solution
Answer: Option B
Solution:
Let the required number of men be xMore days, Less men (Indirect proportion)