30 men can do a piece of work in 16 days. How many men would be required to do the same work in 20 days ?

A.
12
B.
24
Answer
C.
36
D.
48
E.
None of these

Answer: Option B

Solution

Answer: Option B
Solution:
Let the required number of men be x
More days, Less men (Indirect proportion)