36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work?
A.
12
B.
18
C.
22
D.
24
AnswerE.
None of these
Answer: Option D
Solution
Answer: Option D
Solution:
Let the required number of days be x.Less men, More days (Indirect Proportion)