Q194
45 men can complete a piece of work in 16 days. Four days they started working , 36 more men joined them. How many days will they take to complete the remaining work ?
A.
6 days
B.
8 days
C.
Answer
D.
Answer: Option C
Solution
Answer: Option C
Solution:
According to the question,Let the remaining work is complete in D days
= +