A and B can do a work in 262/3 days. B and C together can complete the same work in 48 days, while A and C together can complete the same work in 30 days. How long (in days) will A alone take to complete 60% of the work?

A and B can do a work in  days. B and C together can complete the same work in 48 days, while A and C together can complete the same work in 30 days. How long (in days) will A alone take to complete 60% of the work?
A.
24
Answer
B.
36
C.
32
D.
20

Answer: Option A

Solution

Answer: Option A
Solution:

Time and Work mcq question image
2(A + B + C) = 9 + 5 + 8 = 22
(A + B + C) = 11
A = 11 - 5 = 6
60% of total work