A and B can together finish a piece of work in 30 days. They worked on it 20 days and then B left. The remaining work was done by A alone in 20 days. A alone can finish the work in = ?

A.
60 days
Answer
B.
54 days
C.
48 days
D.
50 days

Answer: Option A

Solution

Answer: Option A
Solution:
  (T.W.)
60
2 units/day  
  30 days
(A + B)
  (T.W.)
2 0
1 units/day  
  20 days
(A)
A's efficiency 1 units/day A will complete the whole work in