Q39

A and B completed a work together in 5 days. had A worked at twice the speed and B at half the speed, it would have taken them four days to complete the job. How much time would it take for A alone to do the work?

A.
10 days
Answer
B.
20 days
C.
25 days
D.
15 days
E.
24 days

Answer: Option A

Solution

Answer: Option A
Solution:
Assume work to be done 100%.
First case,
A + B = = 20% work done per day -------- (1)
Second case,
2A + = = 25% work done per day ------ (2)
On solving equation (1) and (2), we get
A = 10 days