A' and 'B' contract that 'A' shall build a house for 'B' at a fixed price. The order in which reciprocal promises are to be performed was not fixed. What shall be the order of performance?
A.
A's promise to build the house must be performed before B's promise to pay for the house
AnswerB.
B's promise to pay for the house must be performed before A's promise to build the house
C.
A & B should perform their promise Simultaneously
D.
None of the above
Answer: Option A
Solution
Answer: Option A
No explanation is given for this question Let's Discuss on Board