Competitive Exams · Aptitude · question 208

Q208

A and B together can do a piece of work in 30 days, B and C together can do it in 20 days, A starts the work and works on it for 5 days, B takes up and work for 15 days. Finally C finishes the work in 18 days. The number of days in which C alone can do the work where doing it separately is = ?

A.
120 days
B.
40 days
C.
60 days
D.
24 days
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
L.C.M. of Total Work =60
One day work of A + B = = 2 unit/day
One day work of B + C = = 3 unit/day

Work done by (A +B) in 5 days
= 2 × 5 = 10 units
⇒ Work done by (B + C) in 10 days
= 10 × 3 = 30 units
⇒ Total work (finished till now).....40 units
⇒ Remaining work
= 60 - 40
= 20 units
⇒ Here we find that C does remaining 20 units in 8 days
⇒ C's efficiency =

⇒ Therefore, time taken by C alone to complete the work