Q202
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed ?
A.
4
B.
5
C.
7
AnswerD.
8
Answer: Option C
Solution
Answer: Option C
Solution:
work is done by A, B ans C in 1 day.
∴ work is done by A, B and C in