A can complete 1/3 of a work in 5 days and B, 2/5 of the work in 10 days. In how many days both A and B together can complete the work ?

A can complete of a work in 5 days and B, of the work in 10 days. In how many days both A and B together can complete the work ?
A.
B.
C.
Answer
D.
10

Answer: Option C

Solution

Answer: Option C
Solution:
Whole work will be done by A in

Whole work will be done by B in


∴ A and B together can complete the work in