Q274
A can do a certain job in 12 days and B is 60% more efficient than A. The B can do the same piece of work in ?
A.
B.
Answer
C.
D.
Answer: Option B
Solution
Answer: Option B
Solution:
Ratio of time, taken by A and B = 160 : 100 = 8 : 5If A takes 8 days, B takes 5 days
If A takes 12 days,
B takes days