A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work. A leaves off. The total number of days to complete the work is ?

A.
B.
C.
Answer
D.

Answer: Option C

Solution

Answer: Option C
Solution:

Now, work is done by A and B in 1 day