Q272
A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in ?
A.
16 days
B.
24 days
AnswerC.
35 days
D.
28 days
Answer: Option B
Solution
Answer: Option B
Solution: