A company calculates the prices of jobs by adding overheads to the prime cost and adding 30% to total costs as a profit margin. Job number Y256 was sold for Rs1690 and incurred overheads of Rs 694. What was the prime cost of the job?

A.
Rs 489
Answer
B.
Rs 606
C.
Rs 996
D.
Rs 1300

Answer: Option A

Solution

Answer: Option A