A company employed 200 workers to complete a certain work in 150 days. If only 1/4 th of the work had been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed were ?

A company employed 200 workers to complete a certain work in 150 days. If only th of the work had been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed were ?
A.
100
Answer
B.
600
C.
300
D.
200

Answer: Option A

Solution

Answer: Option A
Solution: