A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier ?
A.
100
B.
60
C.
75
AnswerD.
None of these
Answer: Option C
Solution
Answer: Option C