A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only 5/8 th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?

A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?
A.
16
Answer
B.
12
C.
10
D.
18

Answer: Option A

Solution

Answer: Option A
Solution: