Vidyalelo
Mechanical Engineering · Q145

Industrial Engineering And Production Management

Engineering and GATE · Mechanical Engineering · question 145

Q145

A critical activity has

A.
Maximum slack
B.
Minimum slack
C.
Zero slack
Answer
D.
Average slack

Answer: Option C

Solution

Answer: Option C
Solution:
A critical activity has Zero slack