Q72
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
A.
23 days
B.
37 days
C.
days
AnswerD.
40 days
Answer: Option C
Solution
Answer: Option C
Solution: