Aptitude · Q28

Time And Work

Competitive Exams · Aptitude · question 28

Q28

A group of 12 men can do a piece of work in 14 days and other group of 12 women can do the same work in 21 days. They begin together but 3 days before the completion of work, man's group leaves off. The total number of days to complete the work is:

A.
B.
C.
Answer
D.
60

Answer: Option C

Solution

Answer: Option C
Solution:
Let x be the required number of days
Given,
12 men and 12 women can complete a work separately in 14 days and 21 days respectively
Then,
12 men's 1 day work =
And,
12 women's 1 day work =
Then ,
12 women's 3 days work = =

The remaining work =   =
Man's group leaves 3 days before the completion of work
That is, they were working together for x - 3 days
Thus, we have work left to be done in last 3 days by the women's group. This also means th of work has been done by both the groups (before men left)
Now, (12 men + 12 women)'s 1 day work =   =
i.e., work is done by 2 groups in 1 day.
So, of work is done by 2 groups together in   = days
Total time take to complete the work will be
= + 3 =