Q26

A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?

A.
1.0 hour per unit
Answer
B.
1.2 hours per unit
C.
1.4 hours per unit
D.
1.6 hours per unit

Answer: Option A

Solution

Answer: Option A
No explanation is given for this question Let's Discuss on Board