A mining company has three mines (MI, M2 and M3) that supply coal to three power plants (P1, P2 and P3). The three mines produce 900. 1000 and 1200 te of coal per day respectively. The power plant requirements from these three mines are 1200. 1000 and 900 te per day respectively. The unit cost of transporting coal from the three mines to the three power plants in Rs. is given below Power Plants P1 P2 P3 Mines M1 8 10 12 M2 12 13 12 M3 14 10 11 Based on the initial basic feasible solution, using Vogel's approximation method, the total transportation cost in Rs. is

A mining company has three mines (MI, M2 and M3) that supply coal to three power plants (P1, P2 and P3). The three mines produce 900. 1000 and 1200 te of coal per day respectively. The power plant requirements from these three mines are 1200. 1000 and 900 te per day respectively. The unit cost of transporting coal from the three mines to the three power plants in Rs. is given below
Power Plants
P1 P2 P3
Mines M1 8 10 12
M2 12 13 12
M3 14 10 11
Based on the initial basic feasible solution, using Vogel's approximation method, the total transportation cost in Rs. is
A.
31200
B.
31400
Answer
C.
32800
D.
40000

Answer: Option B

Solution

Answer: Option B