Vidyalelo
Mining Engineering · Q33

Mine System Engineering

Engineering and GATE · Mining Engineering · question 33

Q33

A mining project comprising of A, B and C activities is scheduled for 90 days at a cost of Rs. 1200 million. The manager of the project decides to reduce the time for completion of the project to 85 days. The decision was taken after 45 days, The minimum cost of the project in million rupees after crashing 5 days is

A mining project comprising of A, B and C activities is scheduled for 90 days at a cost of Rs. 1200 million. The manager of the project decides to reduce the time for completion of the project to 85 days. The decision was taken after 45 days, The minimum cost of the project in million rupees after crashing 5 days is
Mine System Engineering mcq question image
A.
100
B.
1300
Answer
C.
1475
D.
1825

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board