A mining project is composed of five activities whose three time estimates in months are given below:
Activity Estimated duration (months)
Optimistic time Most likely time Permissible time
1-2 1 1 7
1-3 2 5 8
2-4 1 1 7
3-4 2 5 14
4-5 3 6 15
The standard deviation of the project length in months is
A.
2
B.
3
Answer
C.
6
D.
9

Answer: Option B

Solution

Answer: Option B