Vidyalelo
Mechanical Engineering · Q294

Industrial Engineering And Production Management

Engineering and GATE · Mechanical Engineering · question 294

Q294

A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

A.
0.50
B.
0.66
C.
0.84
Answer
D.
0.95

Answer: Option C

Solution

Answer: Option C
Solution:
Standard deviation = square root of (variance) = square root of (1 * 1 + 2 * 2 + 2 * 2) = square root of (9) = 3
D = 20
S = 3 + 8 + 6 = 17
Probability
Now, from Z table probability = 0.84.