Q19
A queue of trucks at a crusher plant hopper is known to be M/M/1 queue. The probability that there is no truck to unload is 0.3. Due to rains the mean service time at the hopper is increased by 30%. As a consequence, the expected number of trucks in the queuing system (including the one possibly unloading) becomes
A.
10
AnswerB.
12
C.
14
D.
16
Answer: Option A
Solution
Answer: Option A
No explanation is given for this question Let's Discuss on Board