Vidyalelo
Mining Engineering · Q38

Mineral Dressing in Mining

Engineering and GATE · Mining Engineering · question 38

Q38

A slurry stream containing quartz is diverted into one litre density can. The time taken to fill up the can is measured as 5 sec. The pulp density is measured to be 1250 kg/m3. Calculate the mass flow rate of quartz within the slurry. Assuming the density of quartz is 2650kg/m3

A.
228 kg/hr
B.
248 kg/hr
C.
275 kg/hr
D.
288 kg/hr
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board