A triangular DRH due to a storm has a time base of 80 hrs and peak flow of 50 m3/sec occurring at 20 hrs from the start. If the catchment area is 144 sq. km the rainfall excess in the storm was

A.
30 cm
B.
15 cm
C.
5 cm
Answer
D.
None of these

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board