A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was ?

A.
100
B.
110
Answer
C.
55
D.
50

Answer: Option B

Solution

Answer: Option B
Solution:
Let total number of worker in beginning is N