Vidyalelo
Mechanical Engineering · Q291

Industrial Engineering And Production Management

Engineering and GATE · Mechanical Engineering · question 291

Q291

Abbreviated work factor data is applied for

A.
Material handling operation
B.
Maintenance operation
C.
Packing and shipping operation
D.
All of these
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
Abbreviated work factor data is applied for
- Material handling operation
- Maintenance operation
- Packing and shipping operation