Activity slack or float of any event on a PERT/CPM chart is represented by

A.
Latest start time of succeeding event earliest finish time of preceding event activity time
B.
Latest start time of the event earliest start time of the event
C.
Latest finish time of event earliest finish time of the event
D.
Anyone of the above
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
Activity slack or float of any event on a PERT/CPM chart is represented by
- Latest start time of succeeding event earliest finish time of preceding event activity time
- Latest start time of the event earliest start time of the event
- Latest finish time of event earliest finish time of the event