An optimum project schedule implies
A.
Optimum utilization of men, machines and materials
B.
Lowest possible cost and shortest possible time for project
AnswerC.
Timely execution of project
D.
To produce best results under given constraints
Answer: Option B
Solution
Answer: Option B
Solution:
An optimum project schedule implies Lowest possible cost and shortest possible time for project