Q227
A's 2 days work is equal to B's 3 days work. If A can complete the work in 8 days, then to complete the work B will take ?
A.
15 days
B.
12 days
AnswerC.
16 days
D.
14 days
Answer: Option B
Solution
Answer: Option B
Solution:
⇒ We know that time is inversely proportional to efficiency
⇒ Then time taken by them in ratio