As per IS specifications, the maximum final setting time for ordinary Portland cement should be

A.
30 minutes
B.
1 hour
C.
6 hours
D.
10 hours
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board