Between the centre of the hole for attaching the detaching hook to the rope shackle and bell plate, when the bucket is at the top of landing, there shall be clear over run space of not less than . . . . . . . . meters.

A.
1.5
B.
2.0
C.
3.2
D.
3.6
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board