Budget which is planned around a single output level is called
A.
marketing budget
B.
methodological budget
C.
static budget
AnswerD.
varied budget
Answer: Option C
Solution
Answer: Option C
Solution:
Budget which is planned around a single output level is called static budget. A static budget is a type of budget that incorporates anticipated values about inputs and outputs that are conceived before the period in question begins.