Check lines (or proof lines) in Chain Surveying, are essentially required

A.
To plot the chain lines
B.
To plot the offsets
C.
To indicate the accuracy of the survey work
Answer
D.
To increase the out-turn

Answer: Option C

Solution

Answer: Option C