Clay layer A with single drainage and coefficient of consolidation Cv takes 6 months to achieve 50% consolidation. The time taken by clay layer B of the same thickness with double drainage and coefficient of consolidation Cv2 to achieve the same degree of consolidation is

Clay layer A with single drainage and coefficient of consolidation Cv takes 6 months to achieve 50% consolidation. The time taken by clay layer B of the same thickness with double drainage and coefficient of consolidation to achieve the same degree of consolidation is
A.
3 months
Answer
B.
6 months
C.
12 months
D.
24 months

Answer: Option A

Solution

Answer: Option A