Q82
Complete installation of computer within 3 months is an example of
A.
rules
B.
programme
C.
project
D.
schedule
AnswerAnswer: Option D
Solution
Answer: Option D
Solution:
Complete installation of computer within 3 months is an example of schedule. Schedule management is the process of developing, maintaining and communicating schedules for time and resource. A schedule is the timetable for a project, programme or portfolio.