Q213
Consider the following loop: MOV CX, 8000H L1 : DEC CX JNZ L1 The processor is running at 14.7456/3 MHz and DEC CX requires 2 clock cycles and JNZ requires 16 clock cycles. The total time taken is nearly
A.
0.01 s
B.
0.12 s
AnswerC.
3.66 s
D.
4.19 s
Answer: Option B
Solution
Answer: Option B
No explanation is given for this question Let's Discuss on Board