Q1147
Consider the following number of activities with their start and finish time given below. In which sequence will the activity be selected in order to maximize the number of activities, without any conflicts? Activity Starting time Finish time A1 1 2 A2 2 5 A3 1 5 A4 3 6 A5 6 8 A6 4 9
Consider the following number of activities with their start and finish time given below. In which sequence will the activity be selected in order to maximize the number of activities, without any conflicts?
| Activity | Starting time | Finish time |
| A1 | 1 | 2 |
| A2 | 2 | 5 |
| A3 | 1 | 5 |
| A4 | 3 | 6 |
| A5 | 6 | 8 |
| A6 | 4 | 9 |
A.
A1, A2, A5
AnswerB.
A1, A2, A3, A4
C.
A1, A3, A5
D.
A1, A2, A5, A6
Answer: Option A
Solution
Answer: Option A
No explanation is given for this question Let's Discuss on Board