Consider the following number of activities with their start and finish time given below. Which of following activity will be left out? Activity Starting time Finish time A1 1 2 A2 3 5 A3 4 6 A4 5 8
Consider the following number of activities with their start and finish time given below. Which of following activity will be left out?
| Activity | Starting time | Finish time |
| A1 | 1 | 2 |
| A2 | 3 | 5 |
| A3 | 4 | 6 |
| A4 | 5 | 8 |
A.
A1
B.
A2
C.
A3
AnswerD.
A4
Answer: Option C
Solution
Answer: Option C
No explanation is given for this question Let's Discuss on Board