Vidyalelo
Data Structure · Q466

Miscellaneous on Data Structures

Programming · Data Structure · question 466

Q466

Consider the following number of activities with their start and finish time given below. Which of following activity will be left out? Activity Starting time Finish time A1 1 2 A2 3 5 A3 4 6 A4 5 8

Consider the following number of activities with their start and finish time given below. Which of following activity will be left out?
Activity Starting time Finish time
A1 1 2
A2 3 5
A3 4 6
A4 5 8
A.
A1
B.
A2
C.
A3
Answer
D.
A4

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board