Cost that has elements of variable and fixed costs at same time is

A.
variable cost
B.
mixed cost
C.
semi variable cost
D.
Both B and C
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
Cost that has elements of variable and fixed costs at same time is mixed cost and semi variable cost.