Q142
Critical Path Net Work helps an engineer
A.
To concentrate his attention on critical activities
B.
To divert the resources from noncritical advanced activities to critical activities
C.
To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D.
All of the above
AnswerAnswer: Option D
Solution
Answer: Option D
Solution:
Critical Path Net Work helps an engineer- To concentrate his attention on critical activities
- To divert the resources from noncritical advanced activities to critical activities
- To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project