Vidyalelo
Computer Science · Q4

Management Information Systems

Engineering and GATE · Computer Science · question 4

Q4

Critical path of the PERT chart is:

A.
path which takes the longest time to complete the project
Answer
B.
the shortest path
C.
both of the above
D.
path which takes the shortest time to complete the project
E.
None of the above

Answer: Option A

Solution

Answer: Option A
No explanation is given for this question Let's Discuss on Board