Vidyalelo
Mining Engineering · Q129

Coal Mining

Engineering and GATE · Mining Engineering · question 129

Q129

Drivage of two sets of roads and forming the pillar called . . . . . . . .

A.
Working in broken
B.
Working in the hole
Answer
C.
Slicing
D.
Longwall advancing

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board