Data Interpretation · Q21

Data Interpretation

Competitive Exams · Data Interpretation · question 21

Q21

Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. the number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.)

A.
150%
Answer
B.
225%
C.
270%
D.
240%

Answer: Option A

Solution

Answer: Option A
Solution:
% change in the cost incurred in the fifth month,