Flexible budget amount is 57000 and flexible budget variance is 14000, then actual result amount will be

A.
$61,000
B.
$71,000
Answer
C.
$43,000
D.
$24,000

Answer: Option B

Solution

Answer: Option B
Solution:
Actual result = Flexible budget amount + Flexible budget variance
= 14000 = $71,000